What we operate and maintain:
The District operates and maintains flood control facilities that have been constructed by the District, or by others and transferred to the District. Routine maintenance is conducted on all District facilities to ensure proper operations. Maintenance typically involves removal of sediment and vegetation to increase conveyance capacity of flood control channels. Also, the District maintains 40 dams or debris basins to remove sediment from channels that have the potential to cause downstream flooding of residential or commercial areas. Storm related maintenance is conducted on an as-needed basis, usually during emergency conditions, to protect life and property. The Division Manager for Operations & Maintenance is Karl Novak.
|  |
 |
 |
Current O&M Projects
|  |
 |
 |
River Parkways Grant Giant Reed Removal 2009
This Project is located at Matilija Dam in Ojai and includes the removal and re-treatment of giant reed, scotch broom, castor bean, salt cedar, and peper trees within an approximate 175 acre site along the Ventura River.
|  |
 |
 |
Arundell Barranca Telegraph Rd to Loma Vista Rd Channel Repair 2009
This project consists of repair of damaged sections of existing slope protection, backfilling eroded channel bank sections, and repairing damaged concrete invert and stabilizer locations.
|  |
 |
 |
Stroube Drain Unit I Gate Installation
This project, located in the City of Oxnard near the 101 freeway and Ventura Road, consists of constructing two reinforced concrete footings, fabricating and installing steel support beams and an operator pedestal, installing a 9 foot by 10 foot slide gate valve, and modifying an existing access grating in accordance with the plans and specifications. The construction is required as a portion of the retrofit of the Stroube Drain levee penetration. The retrofit involves installation of a custom-designed and fabricated isolation valve that will be mounted and will operate within the existing stop log structure.
|  |
 |
 |
Lower Calleguas Levee Road Grade Repair 2009
This project consists of grading approximately 40,830 linear feet of Crushed Miscellaneous Base (CMB) roadway and reestablishing the 1% transverse slope from the wet side to the dry side atop the east and west levees adjacent to the Calleguas Creek. The area to be repaired runs from Hueneme Road to Highway 1.
|  |
 |
 | Operations & Maintenance Mitigation Department
|  |
 |
 |
The Operations and Maintenance Division is divided up into the following four zones:
|  |
 |
 | For a description of Zones 1 & 2
|  |
 |
 | For a description of Zones 3 & 4
|  |
 |